Pedestrian Access to Transit & Crosswalk Improvements

Print
Press Enter to show all options, press Tab go to next option

Crosswalk Enhancements - Diablo at George 
(Example of improvements)

Project Overview

Pedestrian Access to Transit & Crosswalk Improvements (CIP 18-002)

Description

This project would install approximately 450 linear feet of sidewalk, upgrade ADA curb ramps and accessibility features as mandated, median pedestrian refuge, LED flashing signs at the curbs as well as updated striping, signs and pavement markings.


Location

  • DeLong Avenue at Sherman Avenue
  • Diablo Avenue at George Street (Safeway)
  • Redwood Boulevard at Rush Creek Place
  • Novato Boulevard at McClay Road
  • Alameda del Prado at Posada del Sol
  • Topaz Drive between Misty Road and Andale Avenue
  • Redwood Boulevard - North of San Marin Drive (SMART station: Novato North)

 Schedule

Construction work is anticipates to start in Spring/Summer 2018, and should last approximately two months.


 Cost

$435,000 including a $318,000 Lifeline Transportation Program (LTP) Grant comprised of Measure “A” funds from the Transportation Authority of Marin (TAM).


Contact Information

Project Manager  
 Petr Skala, Project Engineer  Public Works Department
 415.899.8237  415.899.8246